• Brewhouse Vessels Arrive in Asheville

    We are incredibly grateful to be surrounded by an exceptional team and community as we undertake what is New Belgium's largest project and investment to date, building an east coast brewery home in Asheville, NC. The second week in January, our Brewhouse vessels arrive, marking a key milestone in this process. Literally hundreds of people from multiple countries have made this possible. We are grateful.  Read the press release New Belgium Asheville, December 2014 - www.oppenheimphoto.com     Brewhouse 2 in Fort Collins, CO    Whirlpool kettle ready for shipment from Germany     Wort Kettle and Mashtun at GEA in ...

     

  • October 31, 2014 - Distribution Center Site Update

    Over the last month at our DC site in Enka-Candler, tilt up walls have been erected and structural Steel is currently being welded on site for roofing.    We expect the building to be enclosed by December and operational by Spring 2015.  

     

  • UPDATED October 31, 2014: BOOerwery Site Update

    HAPPENING NOW Deep Foundation Piles – Anticipated neighborhood impact: 4 of 5 (noise and trucks) The second and final planned installation of deep foundation piles will start around November 10 and be finished within two weeks or less, weather pending. We thank our immediate neighbors for their patience during this process. UPDATE: 11/21/14 - if you live nearby, you may have noticed it's been fairly quiet these last two weeks.  Due to challenges with equipment and increased depth needed for some of the piles, our timeline for pile driving has shifted.  We aim to have pile driving complete before Thanksgiving, but it may continue ...

     

  • October 2, 2014: Site Update - Craven Street

    HAPPENING NOW Malt Silos Preparation – Anticipated neighborhood impact: 2 of 5 (material delivery, setting steelwork for silos) Malt Silos store malt for brewing Malt Silos construction has begun and continues through November.  The Malt Silos are located within the retaining walls on the west end of the site.  The nine silos will be constructed in pieces and then walled in later this year. The process begin in mid-September and you can start see them taking shape. Cellar Foundations- Anticipated neighborhood impact: 3 of 5 (trucks along Riverside and Craven, extended work hours) Foundation work continues and runs through the ...

     

  • September 17, 2014: Site Update - Craven Street

    HAPPENING NOW Malt Silos Preparation – Anticipated neighborhood impact: 3 of 5 (material delivery, setting steel columns) Malt Silos store malt for brewing Malt Silos construction will begin with setting steel columns in the next week and continue through November.  The Malt Silos are located within the retaining walls on the west end of the site.  The nine silos will be constructed in pieces and then walled in later this year. While the process begins in mid-September, visually, you will see it starting to take shape around mid-October. Site Panorama - see the site from the inside    Cellar Foundations...

     

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. Next page