• October 31, 2014 - Distribution Center Site Update

    Over the last month at our DC site in Enka-Candler, tilt up walls have been erected and structural Steel is currently being welded on site for roofing.    We expect the building to be enclosed by December and operational by Spring 2015.  

     

  • October 31, 2014: BOOerwery Site Update

    HAPPENING NOW Deep Foundation Piles – Anticipated neighborhood impact: 4 of 5 (noise and trucks) The second and final planned installation of deep foundation piles will start around November 10 and be finished within two weeks or less, weather pending. We thank our immediate neighbors for their patience during this process. Given the generally unstable soil conditions of our site, certain sections of the brewery and all of the Liquid Center must rely on deep foundation piles, i.e. steel H-beams driven into the ground until reaching bedrock.  This process is loud, with ground vibration being felt by neighbors ...

     

  • October 2, 2014: Site Update - Craven Street

    HAPPENING NOW Malt Silos Preparation – Anticipated neighborhood impact: 2 of 5 (material delivery, setting steelwork for silos) Malt Silos store malt for brewing Malt Silos construction has begun and continues through November.  The Malt Silos are located within the retaining walls on the west end of the site.  The nine silos will be constructed in pieces and then walled in later this year. The process begin in mid-September and you can start see them taking shape. Cellar Foundations- Anticipated neighborhood impact: 3 of 5 (trucks along Riverside and Craven, extended work hours) Foundation work continues and runs through the ...

     

  • September 17, 2014: Site Update - Craven Street

    HAPPENING NOW Malt Silos Preparation – Anticipated neighborhood impact: 3 of 5 (material delivery, setting steel columns) Malt Silos store malt for brewing Malt Silos construction will begin with setting steel columns in the next week and continue through November.  The Malt Silos are located within the retaining walls on the west end of the site.  The nine silos will be constructed in pieces and then walled in later this year. While the process begins in mid-September, visually, you will see it starting to take shape around mid-October. Site Panorama - see the site from the inside    Cellar Foundations...

     

  • August 18, 2014: Distribution Center Site Update

    We’re moving right along with progress on our Distribution Center (DC), starting to pour foundations.  By the end of this week (weather pending) we will pour nearly 2,000 cubic yards of concrete.  That’s roughly 250 concrete truck fulls or enough to pour about 120 slabs for a 1,500 SF house! We expect the DC walls to be raised by September 2014 and the building to be complete by Spring of 2015.  We'll ship beer along the East Coast from the DC in Enka-Candler. And, we have a new DC neighbor! Wicked Weed Brewing is building a production brewery next door...

     

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. Next page